They moved on thru Sheridan Avenue – and now they take it higher. After a brief break, the final phase of construction on the Sheridan Avenue rehabilitation project is set to resume in mid-February. WYDOT and primary contractor S&S Builders of Gillette will resume where things were left off: heading up 17th Street to the…

Construction season ends on Sheridan Avenue as the colder temperatures and snowy weather of the winter season settles into Cody. Phase 2 of the Sheridan Avenue rehabilitation project concludes due to the persistent winter weather currently enveloping Cody. In the last weekly update of 2020, WYDOT and primary contractor S&S Builders of Gillette announced that…

The Sheridan Avenue rehabilitation project is making excellent progress – so don’t be surprised if you see the construction continuing into mid-December. As of this week, the east side intersection at Alger Avenue and 17th Street is closed – the final step of Phase 2 of the Sheridan Avenue rehabilitation project. Everything is going smoothly,…

The recent cold weather slowed things down, but Phase 2 of the Sheridan Avenue rehabilitation project is still moving forward and on track to stay on schedule. Cody Beers, WYDOT Public Relations Specialist, says the recent sub-zero temperatures delayed their efforts a few days. Forecasts call for consistently higher temperatures this week and beyond, so…

A vehicle forcing its way through the Sheridan Avenue work zone could lead to increased law enforcement to ensure worker safety. WYDOT spokesman Cody Beers related the harrowing incident where a pickup truck forced into the work zone, despite the signs and barriers designating the road was closed. Around 5:30 p.m. Monday evening, a pickup…

An incident of vandalism during the Sheridan Avenue Project cost thousands of dollars and days of unnecessary delays to the time-sensitive project. Phase 2 of the Sheridan Avenue Project continues this week, with work switching over to the westbound lanes sometime Wednesday. The contractor, S&S Builders, is capitalizing on the warm, dry weather to move…

As progress on the $4.93 million-dollar Sheridan Avenue rehabilitation project moves forward, work enters the night grinding stage. Starting next Monday, September 21, concrete grinding will begin between 14th and 15th Streets on side of Sheridan, and Beck and Alger Avenues on the other. The hours for this work will be between 9 PM and…

The work resumes and continues. It’s now 1 week into Phase 2 of the Sheridan Avenue Rehabilitation project, and the results are speaking for themselves. The Alger Avenue Intersection with 17th Street reopens today, while the Beck Avenue Intersection at 17th will simultaneously close.  The work continues crawling along – concrete slab replacement, curb and gutter,…

It’s time to tear up Sheridan once again. August 24th is the official start date of the 2nd phase of the Sheridan Avenue rehabilitation project. Its going to be more of the same work Cody was becoming accustomed to until the work stopped for the summer on June 15th.  Concrete “panels” in the road will…

Sheridan Avenue’s facelift is moving along swimmingly. WYDOT held another community update yesterday at its new time and location: 9 am on the porch of the Irma Hotel, which will be the location of all weekly construction meetings for the discernible future. While business and pedestrian activity has slowed down, construction is literally chipping and…