Two years of intense construction on Sheridan Avenue finish ahead of schedule, which should keep traffic in Cody moving without interruption for decades. Sheridan Avenue is getting its finishing touches this week. After two years of intense construction, the Sheridan Avenue rehabilitation project is nearly finished. Todd Frost, W.Y.D.O.T. resident engineer in Cody, shared the…

It’s the report Cody has been waiting for – after two years and dozens of traffic alterations, “the end of the road” is near on Sheridan Avenue. WYDOT has released its latest update on the progress of the Sheridan Avenue rehabilitation project. Work on the massive road project throughout Cody continues this week, but the…

After two delays, it’s time for the Sheridan Avenue rehabilitation project to slow down and go downhill – so you’ll want to plan your Cody drive accordingly. Starting Thursday, April 1, fifty trucks and 500 cubic yards of concrete will be poured down 17th Street towards Alger Avenue. When the pour commences, one-way traffic with…

Winter weather has delayed the massive concrete pour planned on 17th Street, with the new pour and related traffic delays now planned for Thursday, April 1. Once again, the weather is delaying the massive concrete pour down 17th Street Hill. Winter weather has forced the rescheduling of the large downhill concrete pour planned on the…

Winter weather has caused another delay on Sheridan Avenue, as construction workers are hoping and waiting for the ongoing project to start going downhill. WYDOT announced that the Sheridan Avenue rehabilitation project had encountered another delay. Due to the week’s winter weather, the massive concrete pour planned for this week has been postponed. 2021 has…

After two weeks of weather-related delays, the next and hopefully final phase of construction on Sheridan Avenue will begin the push up the Greybull Hill. The Sheridan Avenue rehabilitation project resumes its work today. WYDOT and S&S Builders, the primary contractor, will begin sectioning off the downhill side of 17th Street in anticipation of the…

Another week, another delay on Sheridan Avenue – but not the type you might be thinking of. WYDOT has announced another delay to the beginning of the final phase of the Sheridan Avenue rehabilitation project. This is the second delay to the work in 2021. Freezing temperatures prevented construction from resuming on the intended start…

There are several weather-related obstacles for Cody traffic to avoid on the Greybull Hill – but construction barrels won’t be among them for another week. Cody’s sudden turn into sub-zero temperatures has delayed the intended start of the final phase of the Sheridan Avenue rehabilitation project. WYDOT announced that the intended start of Phase 3…

They moved on thru Sheridan Avenue – and now they take it higher. After a brief break, the final phase of construction on the Sheridan Avenue rehabilitation project is set to resume in mid-February. WYDOT and primary contractor S&S Builders of Gillette will resume where things were left off: heading up 17th Street to the…

Construction season ends on Sheridan Avenue as the colder temperatures and snowy weather of the winter season settles into Cody. Phase 2 of the Sheridan Avenue rehabilitation project concludes due to the persistent winter weather currently enveloping Cody. In the last weekly update of 2020, WYDOT and primary contractor S&S Builders of Gillette announced that…